Grupo Mar

Grupo Mar

PROJECT DEVELOPMENT

2015 - PLANT EXPANSION OF PACKAGING , LABELING AND STORAGE CANS

2015 - BUILDING A NEW FISH FREEZER STORE

PLANT EXPANSION OF PACKAGING , LABELING AND STORAGE CANS

In order to provide greater accommodation to catch boats Group and to serve as a buffer warehouse and supply of fish from the adjacent plant, services Detail Engineering and Technical Assistance with the following scope is hired:

Consultancy

Engineering for improved productivity

Phase of final design:

Initial design of the plant
Layout design
Counselling the client throughout the process
Design and definition of the civil works to be done
Design and definition of the utilities

Phase of project management :

Counselling about the selection of suppliers
Supervision and control of civil works and utilities execution

Permits and legalisations:

Obtaining all the permits prior to the execution of the plant, as well as the legalisation of the same before all the competent authorities.

BUILDING A NEW FISH FREEZER STORE

In order to provide greater accommodation to catch boats Group and to serve as a buffer warehouse and supply of fish from the adjacent plant, services Detail Engineering and Technical Assistance with the following scope is hired:

Phase of final design:

Initial design of the plant
Layout design
Counselling the client throughout the process
Design and definition of the civil works to be done
Design and definition of the utilities

Phase of project management :

Counselling about the selection of suppliers
Supervision and control of civil works and utilities execution

Permits and legalisations:

Obtaining all the permits prior to the execution of the plant, as
well as the legalisation of the same before all the competent
authorities.